Valdosta, GA - Construction has already begun on the two mains that will be available to residents in Annexed Islands 27, 35B, and 77C if they choose.

The ity will host a public meeting on Wednesday at 6 pm in the Valdosta City Hall Annex Room, located at 300 N. Lee Street, for homeowners and residents affected by the Annexed Islands Construction Schedule.

"They're definitely going to affect the motorists and the people traveling public. Basically it's the construction. We have, within the neighborhoods we will have water and sewer extended to them, but also we have to connect to the mains, which run along the main roads" says Jim Martinez, Engineering Project Manager for the City of Valdosta.

Martinez says commuters and homeowners in the area can expect lane closures during the construction.

According to The City, Annexed Island 27 is located in the Highland Heights area, which includes Bemiss Road, Tomlinson Road, Heirs Street, Hamm Street, Highland Heights Drive, 1st, 2nd & 3rd Streets, Gard Street and Highland Heights Lane. Annexed Island 35B is located in the Pineridge Subdivision area, which includes Betty Jo Drive, Thea Lane, Simpson Place, Briggs Street, Jadan Place and Walmar Place. Annexed Island 77C is located in the St. Augustine Northwest area and includes Kelly Drive, Colin Drive, Maude Street, Chaney Street and Jordan Drive.

Construction work for these annexed islands will consist of installing a new 8-inch Polyvinyl chloride (PVC) sanitary sewer main, sanitary sewer manholes, 6-inch sewer services, 8-inch PVC water main, 8-inch ductile iron (D.I.) water main, water valves and fittings, fire hydrant and valves, and water services. The scope of the projects also involves removing and replacing driveways and pavement, monitoring traffic control and erosion control, and other related work.

The construction projects, which will begin this week, will take approximately 210 days to complete, weather permitting. Traffic barricades, barrels, and signage will be installed in place to alert the traveling public of the construction. Motorists are urged to adhere to all warning signs and drive with extra caution, for their safety and the safety of the construction workers.

For additional information, contact the City of Valdosta Engineering Department at (229) 259-3530.